Net Metering by State

What your electric utility actually pays for exported solar power.

North Dakota solar export compensation

What North Dakota pays for exported rooftop solar power, with the source and the date each figure was checked.

Record verified 2026-09-16 · 10 of 17 fields sourced

What does your utility pay?

Fixed export rate

Base Avoided Costs $0.04571 per kWh; Renewable Energy Credit $0.00096 per kWh; Solar Renewable Energy Credit $0.00300 per kWh.

Otter Tail Power (North Dakota) · North Dakota

Effective Effective with bills rendered on and after June 1, 2026.

The rider is available to any Qualifying Facility not exceeding 100 kW; it says the customer is compensated monthly for all energy received from the small qualifying facility less the customer charge.

Source: otpco.com

Full Otter Tail Power (North Dakota) detail →

North Dakota's cited statewide rule is N.D.A.C. chapter 69-09-07, which applies to sales and purchases between qualifying facilities and electric utilities. Qualifying facilities with a design capacity of 100 kW or less are entitled to net energy billing, while purchases outside that standard arrangement are based on the purchasing utility's avoided costs. The rule's text and its filed objection identify the requirement as applying to investor-owned electric utilities; rural cooperatives and municipal utilities set their own terms. Otter Tail Power's current North Dakota rider shows a concrete avoided-cost export rate of $0.04571/kWh effective June 1, 2026. Northern Plains Electric Cooperative publishes a separate member buyback rate below 2.4 cents/kWh and a 1.6605-cent/kWh PURPA rate at the time of its publication. Other credit rollover, true-up, and aggregate-cap terms are left unreported where the cited sources do not state them.

Program details

Compensation mechanismQualifying facilities with a design capacity of 100 kW or less are entitled to net energy billing; other qualifying-facility purchases may be based on the purchasing utility's avoided costs.
Export rateNo single statewide dollar export rate is stated. For energy provided as available, purchase rates are based on the purchasing utility's avoided costs calculated at the time of delivery.
Rate effectiveThe statewide rule is identified as amended effective May 1, 1991; current utility-specific terms vary. Otter Tail's cited North Dakota rider is effective with bills rendered on and after June 1, 2026.
Credit rolloverNot yet verified
Credit expirationNot yet verified
Annual true-upNot yet verified
Residential system capQualifying facilities with a design capacity of 100 kW or less are entitled to net energy billing.
Commercial system capQualifying facilities with a design capacity of 100 kW or less are entitled to net energy billing; the cited rule does not state a separate residential or commercial cap.
Aggregate program capNot yet verified
Program statusNot yet verified
RegulatorNorth Dakota Public Service Commission.
DocketOtter Tail's cited North Dakota Small Power Producer Rider was approved in Case No. PU-26-51 by order dated May 14, 2026.
Governing ruleN.D.A.C. chapter 69-09-07, Small Power Production and Cogeneration; the rule identifies N.D.C.C. 49-02-02 as the law implemented.
GrandfatheringNot yet verified
Interconnection applicationFor Otter Tail's small qualifying facilities, the customer must sign a contract; before installation, the customer must furnish a detailed generator and related-equipment diagram for company approval and execute an electric service agreement.
Interconnection timelineFor an optional North Dakota Public Service Commission certification application, the Commission must act within 90 days of a complete filing, or the application is deemed granted if no order is issued within 90 days.
Pending changeNot yet verified

Rates by utility

State rules set the framework. Individual utilities often pay something different, and where they do the utility tariff governs.

Otter Tail Power CompanyBase Avoided Costs $0.04571 per kWh; Renewable Energy Credit $0.00096 per kWh; Solar Renewable Energy Credit $0.00300 per kWh.
Effective with bills rendered on and after June 1, 2026.
The rider is available to any Qualifying Facility not exceeding 100 kW; it says the customer is compensated monthly for all energy received from the small qualifying facility less the customer charge.
Northern Plains Electric CooperativeThe cooperative says its buyback rate is less than 2.4 cents per kWh for systems less than 150,000 watts (150 KW); it states the PURPA purchase rate was 1.6605 cents per kWh at the time of publication.
Northern Plains says members must notify the cooperative, obtain a signed interconnection agreement, and obtain approval before purchasing equipment.
Cass County Electric CooperativeNo published export rate
Cass County's policy publishes a net-billing program for renewable systems less than 40 kW AC and says excess energy is paid at the applicable renewable energy rate; the cited policy does not print the dollar rate.

Sources read for this record

Keep reading